Responses to Performance Engagement Recommendations: Annual Status Update 2024

Tabled: 17 October 2024

Review snapshot

Our performance engagements assess if government agencies are effectively and efficiently meeting their objectives, using resources economically and complying with legislation. 

They often identify opportunities for improvement, which are reflected in our recommendations.

There is no legislative requirement for audited agencies to accept, complete or publicly report on our recommendations. 

We conduct this annual review to monitor how agencies address our findings. This makes agencies’ responses to our recommendations more transparent to the Victorian public and parliamentarians.

Key background information 

This image contains key facts from this review. We made 1,645 recommendations between July 2018 and June 2023 to 108 agencies. In this review we surveyed 56 agencies with 449 unresolved recommendations since 2017.

Source: VAGO.


What we concluded

At this review, most agencies reported that they accept and are implementing our recommendations. Nothing has come to our attention to indicate that agencies are not implementing recommendations they have accepted.

Of the 1,645 recommendations from reports we tabled between July 2018 and June 2023, agencies had:

  • still accepted 1,577 (96 per cent) 
  • completed 1,340 (85 per cent) of accepted recommendations 
  • taken a median of 13 months to complete them.

There are 237 accepted recommendations (15 per cent) that are unresolved. Agencies should complete these recommendations to mitigate the risks we found in their engagements.


What we examined

In this report, we looked at the status of recommendations we made between July 2018 and June 2023. Figure 1 shows the status of these recommendations in December 2023.

Figure 1: Recommendations we examined in this report

Draft Alt Text: Figure 1 is a vertical flowchart with 4 levels summarising the total number of recommendations examined in this report. Each level shows the distribution of recommendations that are accepted, completed, and completed with or without delays. Between July 2018  and June 2023 we made 1,645 recommendations. Of these, 36 were not applicable at this review, and 32 were not accepted at this review. 1,577 recommendations were accepted at this review. Of these, 1,340 were complete, 10 were not started and 227 were in progress. There were 1,115 completed recommendations that had initial target dates. Of these, 436 were completed on or before the initial target date and 679 were completed after the initial target date. There were 369 completed recommendations that had revised target dates. Of these, 223 were completed on or before the revised target date and 146 were completed after the revised target date. There were 15 unresolved recommendations made before July 2018.

*'Not applicable' refers to recommendations that agencies accepted at the time the report was tabled that are no longer being implemented by agencies.
Source: VAGO.

Data dashboard

View the dashboard full screen

Download the raw data

Back to top

How agencies responded to our recommendations

We asked agencies to update us on their progress in implementing our recommendations.

Covered in this section:

Performance engagements and recommendations

This review

We conduct performance engagements to assess if Victorian public sector agencies and their programs and services are operating effectively, economically, efficiently and in compliance with relevant Acts.

Our performance engagements include findings and recommendations to agencies about how they can improve their performance.

We give agencies the opportunity to respond to our recommendations before we table our reports, and we include their responses in our reports. 

Agencies may accept each recommendation in full, in part, in principle or not at all. They may also state the actions they will take to address each recommendation and give a target date for completing them.

We conduct this review each year to ask agencies if they have progressed in completing the recommendations.

Agency

Any public service organisation that meets the definition of a public body under the Audit Act 1994. This includes government departments, local councils, health and education services, and other authorities.

Engagement

An engagement is a performance audit or review that we conduct.

Recommendation

Recommendations refer to the suggestions or advice we provide to an agency about how they can improve their performance.

Tabling date

The tabling date is the date a report is presented to Parliament.


 

Follow-up on
unresolved
recommendations

During this review, we followed up on unresolved recommendations. We asked agencies for updates on:

  • their acceptance of the recommendation
  • what actions they have taken in response to the recommendation
  • if the recommendation is now complete
  • when they completed the recommendation or their updated target date for completion.

This section summarises the recommendation updates agencies have given us. 

For full detail on specific recommendations, see Appendix E or the accompanying dashboard published on our website.


 

Why this is important

We make recommendations to public sector agencies about their programs and services. We aim to help agencies address the root causes of poor performance.

Our recommendations, like the public sector, encompass a broad range of agencies and services. We tabled 94 reports between July 2018 and June 2023 that made 1,645 recommendations to 108 agencies. Government departments received just over half (55 per cent) of the recommendations, followed by local government, which received 27 per cent of the recommendations.

As there are no legislative requirements for agencies to accept, implement or publicly report on actions they have taken, this review provides an update to the public and parliamentarians. It may help them to hold agencies more accountable for how they implement our recommendations.


 

Further information

For more information about the scope of this review and our methods, please see Appendix C. 


 

Consultation with agencies

When reaching our conclusions, we consulted with the reviewed agencies and considered their views. You can read their full responses in Appendix A.


 

Most agencies accepted our recommendations

Acceptance status

Before tabling a report, we ask audited agencies if they accept our recommendations. In this review, we asked agencies again so that we could see if there were any changes.

Of the 1,645 recommendations we made in our reports between July 2018 and June 2023, agencies accepted 1,583 (96 per cent) at time of tabling. At the time of this review, agencies told us that they still accepted 1,577 (96 per cent) (see Figure 2).

Figure 2: Acceptance of recommendations at the time of this review

Figure 2 is a bar chart showing that of the 1,645 total recommendations made, 96% were accepted, 2% were not applicable and 2% were not accepted.

Source: VAGO.

As shown in Figure 3 below, most agencies still accepted the recommendations at the time of this review as they did at tabling. 

Agencies may change the acceptance status to ‘no’ or ‘not applicable’. Common reasons agencies gave for changing their acceptance status included:

  • the recommendations are no longer relevant (circumstances may have changed or other work is underway that makes the recommendation no longer relevant)
  • the agencies do not have the resources (time or budget) to implement the recommendations.

Figure 3: Number of recommendations accepted at the time of tabling and at the time of this review

Figure 3 is a column chart that compares the number of recommendations that were accepted at the time of tabling versus those at the time of this review by tabling year from 2018–19 to 2022–23. The differences in acceptance varies slightly for each year. Numbers peaked in 2018–19 with 576 recommendations at tabling to 561 at review, and then more than halved to 261 at tabling to 259 at review in 2019–20. Numbers increased slightly in 2020–21 with 298 accepted at tabling and 319 at review. In 2021–22, numbers increased to 327 accepted at tabling and 320 at review, before dropping in 2022–23, with 121 recommendations accepted at tabling and 118 at review.

Note: Agencies accepted more recommendations from 2020–21 at this review compared to at tabling. This was because agencies did not initially specify their acceptance status for some recommendations, but later accepted these recommendations at the time of review.
Source: VAGO.


 

Completion of accepted recommendations

We classify recommendations as complete when agencies attest to us that they have established processes to make sure that the recommended action is ongoing. 

Agencies attested:

  • they had completed 1,340 (85 per cent) of the 1,577 accepted recommendations
  • 237 (15 per cent) of the 1,577 accepted recommendations were unresolved. 

Working well: Completion of accepted recommendations

Agencies reported that 85 per cent of the accepted recommendations have been completed. 

We categorise unresolved recommendations as either ‘in progress’ or ‘not started’.

Agencies reported 227 unresolved recommendations were in progress, while 10 were not started. 

Figure 4: Status of accepted recommendations by tabled year

 2018–192019–202020–212021–222022–23Total
Complete536250245266431340
In progress259725368227
Not started0021710

Source: VAGO.


 

Completion by type of agency

We looked at the completion of accepted recommendations by type of agency. Figure 5 shows the percentage and breakdown of accepted recommendations at each stage.

We categorised agencies by type:

  • department
  • council
  • health service
  • TAFE/university
  • water authority
  • others (for example, Victorian Planning Authority, Victoria Police and Parks Victoria).

TAFEs/universities and water authorities reported they had completed all the recommendations we made between July 2018 and June 2023. Departments, councils, other agencies and health services reported they had recommendations that are ‘in progress’ or ‘not started’.

Figure 5: Status of accepted recommendations by type of agency

Figure 5 is a stacked column chart showing the status of accepted recommendations by type of agency. Departments have 83% completed, 16% in progress and 1% not started. Councils have 85% completed, 15% in progress and 0.2% not started. Other agencies have 88% completed and 12% in progress. Health services have 97% completed and 3% in progress. Both water authorities and TAFES or universities have all recommendations completed.
 DepartmentCouncilOtherHealth serviceWater authorityTAFE/ university
Complete713 (83%)370 (85%)144 (88%)83 (97%)20 (100%)10 (100%)
In progress140 (16%)64 (15%)20 (12%)3 (3%)00
Not started9 (1%)1 (0.2%)0000
Total862435164862010

Source: VAGO.


 

Completion by department

Of the 1,645 recommendations we made between July 2018 and June 2023, 903 (55 per cent) were to government departments.

Government departments accepted 862 (96 per cent) of these recommendations. They have completed 713 (83 per cent) of the recommendations they accepted. Figure 6 shows the status of accepted recommendations by department.

Figure 6: Status of accepted recommendations by department 

Figure 6 is a stacked column chart showing the number of completed, in progress or not started recommendations by each department. Departments have completed most recommendations and some are in progress. DEECA has the most amount of recommendations, with 130 completed and 16 in progress. DTP has 97 completed and 16 in progress. DH has 83 completed, 26 in progress and 1 not started. DFFH has 77 completed, 13 in progress and 1 not started. DE has 76 completed and 10 in progress. DTF has 75 completed and 23 in progress. DJSIR has 67 completed and 6 in progress. DPC has 57 completed and 7 in progress. DJCS has 46 completed, 16 in progress and 7 not started. DGS has 5 completed and 7 in progress.

Note 1: Acronyms used are for the Department of Government Services (DGS), Department of Justice and Community Safety (DJCS), Department of Premier and Cabinet (DPC), Department of Jobs, Skills, Industry and Regions (DJSIR), Department of Treasury and Finance (DTF), Department of Education (DE), Department of Families, Fairness and Housing (DFFH), Department of Health (DH), Department of Transport and Planning (DTP), Department of Energy, Environment and Climate Action (DEECA).
Note 2: Department of Government Services (DGS) was established on 1 January 2023.
Source: VAGO.


 

Time agencies take to complete our recommendations

Importance of timely completion of recommendations

Our recommendations aim to address the root causes of poor performance. When agencies complete our recommendations, they help address the issues identified in our performance engagements. 

When we table our performance engagement reports in Parliament, agencies can set target completion dates for the recommendations they accept. They may also revise their target completion dates as many times as needed. 

While some recommendations are more complex than others, agencies should seek to complete recommendations:

  • in a timely manner
  • in accordance with their own target completion dates.

 

Overall time of completion

Agencies took a median of 13 months to complete recommendations tabled between July 2018 and June 2023.

The time taken to complete these recommendations varied from zero to 63 months.


 

Departments’ completion times

Departments took a median of 13 months to complete their recommendations.

Specifically, we found: 

  • DGS had the longest median completion time at 22 months. However, it is important to note that DGS was established on 1 January 2023. Recommendations to DGS were transferred from other departments after functions and responsibilities were reallocated.
  • DPC had the second-longest median completion time at 19 months.
  • DTF had the shortest median completion time at 10 months.
  • DEECA completed the highest number of recommendations (130) at a median of 13 months.

Figure 7: Recommendations completed by departments against median completion times 

Figure 7 is a column chart showing the number of recommendations that were completed by each department, with their respective median completion times. DEECA completed 130 recommendations with a median completion time of 13 months. DTP completed 97 recommendations in a median of 13 months. DH completed 83 recommendations in a median of 13 months. DFFH completed 77 recommendations in a median of 13 months. DE completed 76 recommendations in a median of 12 months. DTF completed 75 recommendations in a median of 10 months. DJSIR completed 67 recommendations in a median of 13 months. DPC completed 57 recommendations in a median of 19 months. DJCS completed 46 recommendations in a median of 13 months. DGS completed 5 recommendations in a median of 22 months.

Note: Recommendations to DGS were transferred from other departments after DGS was established in 2023. Two of these recommendations were completed before they were transferred.
Source: VAGO.


 

Agencies’ target completion dates 

Initial target completion dates

Agencies may set target completion dates for recommendations before a performance engagement tables in Parliament. Of the 1,577 accepted recommendations made between July 2018 and June 2023, 1,333 had an initial target date (85 per cent). The median target date agencies set was 7 months after tabling.

Agencies completed 436 (33 per cent) of the recommendations by the initial target date. Agencies completed 679 recommendations (51 per cent) after the initial target date. 

The maximum delay from the initial target date was 49 months.

Key issue: Initial target dates unmet

Half the recommendations were completed later than their initial target completion dates.


 

Revised target completion dates

During our annual review, we ask agencies if they have changed their target completion date for a recommendation.

Of the 1,333 accepted recommendations with an initial target completion date, agencies changed that date for 556 recommendations (42 per cent) by a median of 14 months. Of these, 90 per cent were further extended. 

Of the 556 recommendations with changed dates, 324 have been reported as ‘completed’.

The median revised target date set by agencies was 25 months after tabling.


 

Not meeting revised target dates

Some agencies still did not meet their revised target completion dates despite revising them.

Of the 324 recommendations with revised target dates, agencies completed 135 (42 per cent) later than their revised dates. The length of additional delay was at a median of 61 days, or about 2 months.

Key issue: Some recommendations have been further delayed

Despite revisions, some agencies still did not meet their revised target completion date. 


 

Status of unresolved recommendations

There are 237 accepted but unresolved recommendations. 

Agencies set initial target completion dates for 218 of these unresolved recommendations. As at 31 December 2023, these unresolved recommendations were a median of 6 months behind their initial target dates. 

Agencies have set revised target dates for 179 of these unresolved recommendations. The length of delay from their initial to revised target dates was at a median of 21 months.


 

Unresolved recommendations made before July 2018

Older recommendations

We requested updates on 23 unresolved recommendations made before July 2018. 

Of these, 15 remain unresolved after this review. These relate to 7 agencies across 5 engagements. 

These older recommendations have been tabled for a median of 69 months (over 5 years). 

We urge the relevant agencies to resolve these recommendations. This will address the risks we found and make necessary improvements.

Key issue: Unresolved older recommendations

At this review, there are 15 recommendations made before July 2018 that remain unresolved. 

Figure 8: Audits made before July 2018 with unresolved recommendations (in order of tabling date)

Audit titleUnresolved recommendationsResponsible agencyTabling date
Managing Public Sector Records4DGS8 March 2017
ICT Disaster Recovery Planning1DFFH29 November 2017
ICT Disaster Recovery Planning2DH29 November 2017
Protecting Victoria’s Coastal Assets3East Gippsland Shire Council29 March 2018
Protecting Victoria’s Coastal Assets1Great Ocean Road Coast and Parks Authority29 March 2018
Protecting Victoria’s Coastal Assets2Mornington Peninsula Shire Council29 March 2018
Safety and Cost Effectiveness of Private Prisons1DJCS29 March 2018
Community Health Program1DH6 June 2018

Source: VAGO.


Back to top

Appendix A: Submissions and comments

Download a PDF copy of Appendix A: Submissions and comments.

 

Download PDF

Download Appendix A: Submissions and comments

Back to top

Appendix B: Abbreviations, acronyms and glossary

Download a PDF copy of Appendix B: Abbreviations, acronyms and glossary.

 

Download PDF

Download Appendix B: Abbreviations, acronyms and glossary

Back to top

Appendix C: Review scope and method

Download a PDF copy of Appendix C: Review scope and method.

 

Download PDF

Download Appendix C: Review scope and method

Back to top

Appendix D: Performance engagements and agencies in this review

Download a PDF copy of Appendix D: Performance engagements and agencies in this review.

 

Download PDF

Download Appendix D: Performance engagements and agencies in this review

Back to top

Appendix E: Agency responses to assurance review

Download a PDF copy of Appendix E: Agency responses to assurance review.

 

Download PDF

Download Appendix E: Agency responses to assurance review

Back to top