2. Is the Metro Tunnel Project progressing as planned?
Conclusion
The tunnels and stations main works are currently progressing as planned and RPV and CYP’s systems for monitoring and achieving project requirements are effective.
However, the overall project is facing time and cost pressures and RPV has allocated almost all its MTP contingency funds. RPV has also descoped some MTP signalling works and wider network enhancements. RPV also needs to formalise agreements with precinct stakeholders to implement EMI mitigations before train testing starts in June 2023.