What we found

This section summarises our key findings. The numbered sections detail our complete findings, including supporting evidence.

When reaching our conclusions, we consulted with the audited entities and considered their views. The entities' full responses are in Appendix A. 

2. Planning and delivering congestion solutions

When congestion initiatives are poorly planned it is more difficult to deliver and assess their benefits.

The department did not design strategic objectives for the signals program. This had consequences for setting priorities and measuring outcomes. 

Similarly, the lack of a benefits management plan for the Hoddle project compromised the authority's ability to assess project benefits.